Time-Lapse Shows the Roof Installation at Madrid's Wanda Metropolitano Stadium

On Thursday, July 29th, the Estadio Wanda Metropolitano's roof was officially completed. This new stadium, a renovation of the old Peineta athletics stadium, is the new home ground of Spanish football club Atlético Madrid.

In this video, FCC Construcción captures the intense work on the roof which was designed and constructed by engineers Schlaich Bergermann Partner. The milestone marks four months of intense work since the installation of the first of the 96 PTFE radial panels at the north end of the stadium.

© FCC

As Cruz y Ortiz Arquitectos explain:

The roof is made of two large rings. The first is a double outer perimeter ring with a tridimensional double truss shape that largely holds the tensional forces of the roof thanks to its geometry. A central double traction ring collects part of roof's load and the tension forces, creating the oversized roof that is clearly the signature of the project.

With the roof completed, the construction of the new Spanish stadium continues toward its official opening on the 16 or 17 of September, when Atlético Madrid are up against Málaga in the fourth round of the Spanish league.

© FCC
© FCC
© FCC
© FCC
© FCC
© FCC
© FCC
© FCC
© FCC
© FCC
© FCC
© FCC

Thanks to FCC Construcción and Cruz y Ortiz Arquitectos.

Image gallery

See allShow less
About this author
Cite: Valencia, Nicolás. "Time-Lapse Shows the Roof Installation at Madrid's Wanda Metropolitano Stadium" [Este timelapse revela cómo se levantó la cubierta del Wanda Metropolitano en Madrid] 03 Sep 2017. ArchDaily. (Trans. Pimenta, Amanda ) Accessed . <https://www.archdaily.com/877598/time-lapse-shows-the-roof-installation-at-madrids-wanda-metropolitano-stadium> ISSN 0719-8884

© FCC

马德里万达大都会体育馆屋顶安装延时摄影

You've started following your first account!

Did you know?

You'll now receive updates based on what you follow! Personalize your stream and start following your favorite authors, offices and users.